Blacktopping of Bhojpur airport runway to miss completion deadline



Bhojpur, March 8: The blacktopping of the runway at the only airport at Bhojpur headquarters is unlikely to meet the completion deadline.

The airport is 545 meters in length and 20 meters in width and only 65 per cent of the total upgradation work has been completed so far.

The upgradation work started on December 9 and should have completed today as per its objective to finish off the work in three months’ time. The unfinished work has prompted the District Administration Office (DAO), District Development Committee (DDC) and security bodies to start inspection and monitoring.

The contractor company, on the other hand, has cited lack of diesel as hampering their work. RSS